 Skip Navigationhome / study / business / accounting / accounting questions and answers / orthopedics of central omaha…Question: Orthopedics of Central Omaha is converting the filing system from alphabetic to terminal digit. T…Orthopedics of Central Omaha is converting the filing system from alphabetic to terminal digit. The front office staff consists of 8 FTEs. The practice manager has given instructions that the work can begins on Friday afternoon as soon as the last patient leaves, which is typically 5pm. The project must be completed by 8:00 am Monday morning.
The HIM coordinator has been collecting information for you in the planning process. There are 2249 medical records. It takes 2 minutes per chart to convert from alphabetic to terminal digit.
Question: How many people will be needed to complete the project in the time frame given?
Expert Answeranonymusanonymusanswered thisThere are 2249 medical records and it takes 2 minutes per chart to convert from alphabetic to terminal digit.
Total minutes required = 2249 records x 2 minute per record = 4498 minutes
Total hours required = 4498 minutes / 60 minutes = 75 hours.
Here we are assuming that the work has to be done in the day shift only.
We have two days, i.e. Saturday and Sunday from 8.00 am to 5.00 pm. 9 hours per day shift
Number of people needed = 75 hours / 18 hours per person = 4.166 rounded to 5 people needed to complete the project in the time frame given.
0 CommentsWas this answer helpful?
0
1Practice with similar questionsOrthopedics of Central Omaha is converting the filing system from alphabetic to terminal digit. The front office staff consists of 8 FTEs. The practice manager has given instructions that the work can begins on Friday afternoon as soon as the last patient leaves, which is typically 5pm. The project must be completed by 8:00 am Monday morning. The HIM coordinator has been collecting…See answer100% (1 rating)Orthopedics of Central Omaha is converting the filing system from alphabetic to terminal digit. The front office staff consists of 8 FTEs. The practice manager has given instructions that the work can begins on Friday afternoon as soon as the last patient leaves, which is typically 5pm. The project must be completed by 8:00 am Monday morning. The HIM coordinator has been collecting…See answer100% (1 rating)
Questions viewed by other studentsEastern Omaha Neurology Center is converting its filing system from alphabetic to terminal digit. There are 15 office staff members. The practice manager has given instructions that the work can begin on Friday afternoon as the last patient leaves, which is typically 2:00 pm. The project must be completed by 8:00 pm Sunday night. The HIM coordinator has been collecting information…See answer100% (1 rating)Eastern Omaha Neurology Center is converting its filing system from alphabetic to terminal digit. There are 15 office staff members. The practice manager has given instructions that the work can begin on Friday afternoon as the last patient leaves, which is typically 2:00 pm. The project must be completed by 8:00 pm Sunday night. The HIM coordinator has been collecting information…See answer100% (1 rating)Show more
On Sun, Dec 2, 2018 at 8:47 PM topnotch writers <[email protected]> wrote:

PROJECT STAFFING MANAGEMENT PROPOSAL
Filing System Conversions 
As an HIM assistant director, you have been asked by administration to help with the filing system conversions at 2 of the outpatient service facilities of your healthcare system. They have asked you to help them in calculating the number of employees needed to complete their projects. 
Project 1 
Orthopedics of Central Omaha is converting the filing system from alphabetic to terminal digit. The front office staff consists of 8 FTEs. The practice manager has given instructions that the work can begin on Friday afternoon as soon as the last patient leaves, which is typically 5:00 p.m. The project must be completed by 8:00 a.m. Monday morning. 
The HIM coordinator has been collecting information for you to use in the planning process. There are 8,950 medical records. It takes 2 minutes per chart to convert from alphabetic to terminal digit. 
1. Determine the number of hours that you expect the project to take. 
2. Can everything be done by working the day shift, or will you need an evening and/or night shift to get the job completed on time? 3. How many people will be needed to complete the project in the time frame given?
Project 2 
Eastern Omaha Neurology Center is converting its filing system from alphabetic to terminal digit. There are 15 office staff members. The practice manager has given instructions that the work can begin on Friday afternoon as soon as the last patient leaves, which is typically 2:00 p.m. The project must be completed by 8:00 p.m. Sunday night. The HIM coordinator has been collecting information for you to use in the planning process. There are 54,760 medical records. It will take 3.5 minutes per chart to convert from alphabetic to terminal digit filing. 
1. How many hours do you expect the project to take? 
2. How long will a shift be? 
3. How many people will be needed to complete the project in the time frame given? 
4. Can everything be done by working the day shift, or will you need an evening and/or night shift to get the job completed on time?
ADDITIONAL REQUIREMENTS 
The paper will be titled,
PROJECT STAFFING MANAGEMENT PROPOSAL
This case study requires a cogent and complete proposal that not only answers the questions above, but discusses good practices for successful electronic health record projects with emphasis on human resources estimating, and best practices converting to electronic medical records. As part of the paper please discuss the following:

1. Converting to terminal digit filing of medical records- best practices.
1-3 pages – 3 or more sources 
2. Project human resources planning
2-3 pages – 3 or more sources
3. Other relevant topic (optional)
Suggested resources for the project
http://library.ahima.org/PdfView?oid=97272
https://www.dummies.com/careers/project-management/pmp-certification/what-you-should-know-about-the-human-resource-management-plan-for-the-pmp-certification-exam/
Google “How to convert to a terminal digit filing system”
Google “staffing management plan 

  

CLIENT TESTIMONIALS

The Service Is Okay. I won’t Complain

The writers on the website are courteous and the customer service responds quickly. My paper was handled well; They promised...

Writers here are very professional and are native British

Thanks a lot for helping me out with my PhD Thesis, Writers here are very professional and are native British!!

Jack, The United Kingdom

Very Very Helpful, and On time.

Very Very Helpful, and On time.

Adelio M, Spain

I scored complete A’s in 3 out of four courses

I scored complete A’s in 3 out of four courses

Anonymous, Illinoi Chicago

CLICK HERE  To order your paper

About Essaysmiths Assignment writing service

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for upto 20% off in their first Order. Our payment method is safe and secure.

 CLICK HERE to Order Your Assignment

 

Recently Posted Questions.

Order your Assignment today and save 15% with the discount code ESSAYHELP

X